On Feb. 15, 2023, the U.S. District Court for the Northern District of Texas held that the force majeure provision contained in the parties’ contract applied to excuse performance even if the event — Winter Storm Uri — did not render performance impossible.

In MIECO LLC v. Pioneer Natural Resources USA, Inc., 2023 WL 2064723, the parties had entered into an agreement in which MIECO (Buyer) would purchase 20,000 million British thermal units of natural gas from Pioneer (Seller) each day from Nov. 1, 2020, to March 31, 2021. But from Feb. 14, 2021, to Feb. 19, 2021, Pioneer failed to deliver the full amount of the contracted natural gas due to Winter Strom Uri. On Feb. 16, 2021, Pioneer sent MIECO a notice of force majeure.

Continue Reading Winter Storm Uri Qualifies as Force Majeure, Even When Performance Was Not “Impossible”